# Deck Construction

This section assigns deck elements to construction stages.

{% hint style="info" %}
**Navigation:** Construction > Superstructure Construction > Deck Construction

For detailed parameter explanations, see the [Deck Construction Reference](https://docs.openbrim.org/templates/concrete-u-girder-bridge-workflow/construction-cug/superstructure-construction-cug/deck-construction-cug).
{% endhint %}

## Steps

### Step 1: Navigate to Deck Construction

Navigate to **Construction > Superstructure Construction > Deck Construction** in the tree view.

### Step 2: Define Pouring Sequence

Assign deck segments to stages representing the concrete pour sequence.

### Step 3: Configure Pour Regions

If deck is poured in multiple regions, assign each region to the appropriate stage.

## Verification

{% hint style="success" %}
After completing these steps, deck construction is staged for time-dependent analysis.