Girder Construction (Segmental)
This section defines the segmental erection sequence for U-girder segments.
Steps
Step 1: Navigate to Girder Construction
Navigate to Construction > Superstructure Construction > Girder Construction in the tree view.
Step 2: Define Segment Erection Sequence
Create construction stage assignments for each girder segment in erection order.
Step 3: Include Closure Pours
Assign closure pour elements to stages after adjacent segments are in place.
Step 4: Coordinate with Temporary Supports
Ensure temporary support stages align with girder segment erection.
Verification
After completing these steps, the segmental girder erection sequence is defined.