Pier Footing Code Check T
This section configures the code check template for pier footing design verification.
Steps
Step 1: Navigate to Pier Footing Code Check T
Navigate to Templates for Code Check > Pier Footing Code Check T in the tree view.
Step 2: Configure Flexure Checks
Set parameters for footing flexural verification:
Bottom reinforcement for positive moment
Top reinforcement for pile uplift (if applicable)
Step 3: Configure Shear Checks
Set parameters for footing shear capacity:
One-way shear (beam shear)
Two-way shear (punching shear)
Critical section locations
Step 4: Configure Bearing Pressure Checks
Set allowable bearing pressure limits based on geotechnical recommendations.
Verification
After completing these steps, the pier footing code check template is ready for design verification.
Last updated