> For the complete documentation index, see [llms.txt](https://docs.openbrim.org/llms.txt). Markdown versions of documentation pages are available by appending `.md` to page URLs; this page is available as [Markdown](https://docs.openbrim.org/templates/precast-i-girder-bridge-workflow/load-rating-pig.md).

# Load Rating \[PIG]

**Staged Construction Analysis**\
For a typical load rating project, a staged construction analysis is performed in the following stages:\
**Stage 1:** Construction of girders and bracings, followed by the application of non-composite loads such as deck loads and stay-in-place formwork loads on the non-composite girder.\
**Stage 2:**(or more): The deck gains stiffness based on the deck pouring sequence.\
**Stage 3:** Barrier loads or wearing surface loads are applied on the deck.\
**Stage 4:** Influence surface-based live load analysis is conducted using various vehicles.

To comply with AASHTO clause`6.10.1.1.1b` , users are given the ability to override the modulus of elasticity of the deck at each stage AASHTO clause `6.10.1.1.1b`. For transient loads assumed to be applied to the short-term composite section, the concrete deck area is transformed using the short-term modular ratio, n. For permanent loads assumed to be applied to the long-term composite section, the concrete deck area is transformed using the long-term modular ratio, 3n.).

**Load Rating**

To compute stress values for load rating, we classify the analysis results from staged construction analysis into three categories: non-composite major axis bending moment, short-term composite bending moment, and long-term composite bending moment.

For positive flexure regions, stress is then calculated based on these three section moduli (girder only-noncomposite section, short-term composite section - deck(n)+girder, and long-term composite section-deck(3n)+girder).

For negative flexure regions, we utilize a non-composite section and a girder section with rebars (optionally with a creep correction factor).


---

# Agent Instructions
This documentation is published with GitBook. GitBook is the documentation platform designed so that both humans and AI agents can read, navigate, and reason over technical content effectively. Learn more at gitbook.com.

## Querying This Documentation
If you need additional information that is not directly available in this page, you can query the documentation by asking a question.

Perform an HTTP GET request on the following URL with the `ask` and `goal` query parameters:

```
GET https://docs.openbrim.org/templates/precast-i-girder-bridge-workflow/load-rating-pig.md?ask=<question>&goal=<user_goal>
```

`ask` is the immediate question: it should be specific, self-contained, and written in natural language.
`goal` is what the user is ultimately trying to achieve, the reason they need the answer. Sharing it helps GitBook give you a better, more relevant answer. A goal is most helpful when it describes the outcome the user wants rather than restating the question. For example, with `ask=how do I create an API token`, a goal like `automate deployments from our CI pipeline` lets GitBook tailor the answer to that use case.

The response will contain a direct answer to the question and relevant excerpts and sources from the documentation.

Use this mechanism when the answer is not explicitly present in the current page, you need clarification or additional context, or you want to retrieve related documentation sections.